磨盘山水库坝基渗透稳定研究
引用本文:张立杰,杜新强,廖资生,王洪波. 磨盘山水库坝基渗透稳定研究[J]. 吉林大学学报(地球科学版), 2007, 37(2): 411-416
作者姓名:张立杰  杜新强  廖资生  王洪波
作者单位:1.黑龙江大学 水利电力学院,哈尔滨 150080;2.吉林大学 环境与资源学院,长春 130026;3.鹤岗市气象局,黑龙江,鹤岗 154100
基金项目:黑龙江省水利厅科技研究开发项目(HSKJ2003-01)
摘    要:磨盘山水库兴建遇到的主要地质问题是坝基渗漏及渗透稳定问题,将影响水库工程效益的发挥和大坝的安全运行,需采取适当的渗控工程措施。通过对坝基土颗粒组成及结构的分析,判别可能发生渗透破坏的类型,确定抗渗比降和允许比降。应用Visual MODFLOW进行水库坝区渗流场的三维渗流数值模拟分析,通过对18种渗控计算方案渗流场、渗流要素及防渗效果的统计分析,依据坝基土的允许比降,在安全、经济、合理原则的基础上,确定哈尔滨市磨盘山水库坝基渗控设计首选方案为:左岸防渗长度200 m、帷幕灌浆标准5 Lu。

关 键 词:坝基  三维渗流  渗透稳定  渗控设计  
文章编号:1671-5888(2007)02-0411-06
收稿时间:2006-10-20
修稿时间:2006-10-20

Study on Seepage Stability of Dam Base for Mopanshan Reservior
ZHANG Li-jie,DU Xin-qiang,LIAO Zi-sheng,WANG Hong-bo. Study on Seepage Stability of Dam Base for Mopanshan Reservior[J]. Journal of Jilin Unviersity:Earth Science Edition, 2007, 37(2): 411-416
Authors:ZHANG Li-jie  DU Xin-qiang  LIAO Zi-sheng  WANG Hong-bo
Affiliation:1. College of Water Resources and Electric Engineering,Heilongjiang University, Harbin 150080,China;2. College of Environment and Resources, Jilin University, Changchun 130026,China;3. Hegang Municipal Meteorological Bureau, Hegang,Heilongjiang 154100,China
Abstract:The geological problems of the building of Mopanshan reservoir is the seepage of the dam base and its stability of infiltration,which will influence the exertion of the engineering benefit and the safely run of the dam and it needs proper measure to control the infiltration.Through the analysis on the granule constitute of the formation of the dam base,the type of the infiltration damage apt to happen has been defined and the anti-infiltration and the permissible depression ratio has also been determined.With the Visual MODFLOW,the three-dimension numerical modeling has been carried out to analyze the see-page field of the reservoir.After the statistics analysis of the seepage factors of the field under 18 different measures and its effect,the seepage-control measure of the Mopanshan reservoir in the city of Harbin is determined that the length of left bank to control the seepage should be 200 m,purdah grouting standard 5 Lu should be the principal measure,according to the permissible depression ratio of the dam base,on the base of safety,economy,principles with reason.
Keywords:dam base  three-dimensional seepage flow  seepage stability  design on seepage control schemes