首页 | 本学科首页   官方微博 | 高级检索  
     检索      

贵南高铁朝阳隧道出口平导6.10突水突泥事件分析
引用本文:付开隆,周羽,韦正雄.贵南高铁朝阳隧道出口平导6.10突水突泥事件分析[J].中国岩溶,2022,41(6):895-904.
作者姓名:付开隆  周羽  韦正雄
作者单位:中铁二院工程集团有限责任公司, 四川 成都 610031
摘    要:2018年6月10日,朝阳隧道出口平导发生岩溶突水突泥,持续时间约1 h,突水突泥总量约1.6×106 m3。为完善施工掘进方案及排水方案,需分析突水突泥产生原因,评价后续施工带来的突水突泥风险,计算隧道涌水量。文章分析了隧道位置的地形地貌、工程地质、水文地质条件,阐述了发生突水突泥的平导掌子面超前地质预报实施情况及突水突泥发生过程,补充调查了灾害影响范围的工程地质、水文地质条件,完成了长达1年的平导涌水量-降雨量关系动态观测。平导突水突泥掌子面前方有水头高达84 m的巨型溶腔及管道系统,施工开挖揭穿溶腔底部后,填充于整个岩溶水系统的有压水流携带泥砂快速涌入平导并以较大动能冲出洞外,导致了6.10突水突泥事件的发生。隧道出口段岩溶水系统接受降雨入渗补给且径流通畅,洞内涌水对应的汇水面积为6.423 km2,计算极端暴雨后平导最大涌水量5×104 m3·h?1。突水突泥发生后山体内的静储量已得到充分释放,地下水位已降至平导底板高程,后续施工中再遭遇突水突泥的风险低。 

关 键 词:突水突泥    溶腔    暗河    原因分析    涌水量    朝阳隧道
收稿时间:2021-11-02

Analysis of 6.10 water and mud inrush incident in the exit of parallel pilot tunnel of Chaoyang tunnel of Guiyang-Nanning high-speed railway
Institution:China Railway Eryuan Engineering Group Co. Ltd, Chengdu, Sichuan 610031, China
Abstract: A high-speed railway running 350 km·h?1 is being built between Guiyang in Guizhou Province and Nanning in Guangxi. Chaoyang tunnel is a double-track single-hole tunnel located in southeastern Guizhou. The tunnel clearance is 100 m2with the total length of 12,734 m (including more than 7-km-long soluble rock), and its maximum burial depth is 386 m. The railroad track elevation of the tunnel is 782-468 m, and it gradually decreases from the entrance to the exit, with a slope of ?22.7‰ to ?25‰. An auxiliary tunnel scheme of "2 transverse tunnels +2 parallel pilot tunnels +1 inclined shaft" has been adopted, with the parallel pilot tunnel on the left side of the main tunnel. The midline of the parallel pilot tunnel is 30 m away from the main tunnel, and 3 m lower than the main hole. The inner headroom size is 5.0 m (width) ×6.0 m (height). Construction of the tunnel began in early 2016 and will be completed in 2022. On June 10, 2018, karst water and mud inrush, lasting about 1 hour, occurred at the exit of parallel pilot tunnel of Chaoyang tunnel. The total amount of water and mud inrush was about 1.6×106 m3. In order to complete the construction tunneling scheme and drainage scheme, it is necessary to analyze the causes of water and mud inrush, evaluate its risk in the subsequent construction, and calculate the water inflow of the tunnel. In this study area, the exit section of the tunnel is in the sloping medium-and-low mountainous area, belonging to the karst peak cluster landform, and the terrain fluctuates greatly. The tunnel passes th exit section of the tunnel is in the sloping medium and low mountainous area, belongs to the karst peak cluster landform with relatively sharp topographic relief. The tunnel passes through a regionally wide and gentle symmetrical anticline, and the exit of the tunnel is located on the southeastern wing of the anticline widely distributed by thick-to-extremely-thick bedded limestone with pure rock texture. Extreme development of surface karst funnels, dissolution basins, karst drop holes, karst caves and other phenomena provides favorable conditions for the collection, infiltration and runoff of surface water, but there is no long-term water system on the surface. After rainfall, the catchment of the non-soluble rock segment is mainly infiltrated through the contact zone between the soluble rock and the non-soluble rock, but the water catchment of the soluble rock section penetrates directly into the underground karst water system through the surface negative topography. Controlled by topography, geomorphology and transverse faults, except for the direction of groundwater seepage along the tectonic line in some sections, the infiltration groundwater is mainly discharged from the Zhangjiang river, which is basically perpendicular to the axis of the anticline and to the southeast wing (the exit of the tunnel). As a result, a series of transverse gullies and underground rivers cutting through the main structural lines were formed. The present study is mainly focused on the following aspects: analyzing the topography, engineering geology and hydrogeology of the tunnel, introducing the implementation of advance geological prediction on the face of the parallel pilot tunnel, and describing the process of water and mud inrush. In this study, the engineering geology and hydrogeology conditions in the area affected by the disaster were investigated and a one-year dynamic observation of the relationship between water inflow and rainfall was also completed. The research finding shows that a huge cavity and pipeline system with a water head of up to 84 m in front of the tunnel face caused the water and mud inrush. After excavation and exposing the bottom of the cavity, the pressurized water flow filling in the whole karst water system carried mud and sand rapidly into the tunnel face and rushed out of the parallel pilot tunnel with a large kinetic energy, resulting in the water and mud inrush event on June 10. In the process of this event, the surrounding karst water system was supplied in time, and the amount of water and mud inrush was much larger than the volume of large dissolution cavity near the tunnel face. The process of "water gushing-water shutoff-water gushing-water shutoff after dredging" occurred many times, indicating that the deposition in the lower part of the cavity is very serious and the drainage is not unobstructed. If the groundwater in the saturated cavity is not discharged effectively, the blasting excavation will cause serious water and mud inrush disaster. Long-term rainfall and water inflow monitoring shows that the karst water system at the exit of the tunnel receives rainfall infiltration recharge and the runoff is unobstructed. The catchment area corresponding to the water inrush to the tunnel is 6.423 km2, and the maximum water inrush in the tunnel after the extreme rainstorm is 5×104 m3·h?1. After the occurrence of water and mud inrush, the static reserves in the mountain body have been fully released, and the groundwater level has dropped to the elevation of the tunnel floor. On the premise of ensuring the unobstructed drainage during the tunneling process, the risk of encountering water and mud inrush in the subsequent construction is low.  
Keywords:
点击此处可从《中国岩溶》浏览原始摘要信息
点击此处可从《中国岩溶》下载免费的PDF全文
设为首页 | 免责声明 | 关于勤云 | 加入收藏

Copyright©北京勤云科技发展有限公司  京ICP备09084417号