长白沿江矿区勘查ZK0902孔施工技术
引用本文:全志刚,王禹,杨春柳.长白沿江矿区勘查ZK0902孔施工技术[J].探矿工程,2010,37(4):34-36.
作者姓名:全志刚  王禹  杨春柳
作者单位:吉林省地矿局第六地质探矿工程大队,吉林延吉133401
摘    要:长白沿江矿区钻探施工中遇到的主要问题是煤系地层水化膨胀,形成陷塘,钻孔坍塌、掉块,深部灰岩蚀变,形成溶洞,严重漏失,导致施工周期延长,现场及时分析原因,采用针对性的工艺措施,成功地解决了上述问题,圆满地完成了矿区施工任务。

关 键 词:煤系地层  绳索取心钻探  陷塘
收稿时间:2009/12/17 0:00:00
修稿时间:2009/12/17 0:00:00

Construction Technology of ZK0902 Exploration Hole in Yanjiang Mine of Changbai in Jilin
QUAN Zhi-gang,WANG Yu and YANG Chun-liu.Construction Technology of ZK0902 Exploration Hole in Yanjiang Mine of Changbai in Jilin[J].Exploration Engineering(Drilling & Tunneling),2010,37(4):34-36.
Authors:QUAN Zhi-gang  WANG Yu and YANG Chun-liu
Institution:(Sixth Geological Prospeting Engineering Team,Jilin Provincial Bureau of Geo-exploration and Mineral Development,Yanji Jilin 133401,China)
Abstract:Hydration swelling in coal measure strata with subsidence pool forming was the main difficulty in drilling construction in Yanjiang mine of Changbai;and hole collapsing,block-falling and deep limestone alteration formed karst cave with serious leakage and long construction period.Field analysis was made to solve the above problems by specific technologies.
Keywords:coal measure strata  wire-line drilling  subsidence pool