高填石路堤蠕变本构模型及其参数反演分析与应用
引用本文:曹文贵,李鹏,程晔. 高填石路堤蠕变本构模型及其参数反演分析与应用[J]. 岩土力学, 2006, 27(8): 1299-1304
作者姓名:曹文贵  李鹏  程晔
作者单位:1. 湖南大学,岩土工程研究所,长沙,410082
2. 湖南省高速公路管理局,长沙,410076
基金项目:中国科学院资助项目;湖南省自然科学基金
摘    要:结合高填石路堤工后沉降变形机理与工程特点,基于工程实测数据,提出了高填石路堤工后沉降蠕变变形的双曲线型三参数本构模型,并引进遗传算法与有限元分析理论,建立了该模型参数的反演分析方法。在此基础上,利用蠕变有限元分析手段,深入探讨了高填石路堤工后沉降的分析计算方法,并开发了相应的分析计算软件。结合某高填石路堤工程实践,探讨了高填石路堤双曲线三参数蠕变本构模型和高填石路堤工后沉降计算的应用方法。工程实例分析表明,提出的本构模型及其工后沉降计算方法简单,可以满足工程要求,初步建立了一种新的高填石路堤工后沉降计算方法。

关 键 词:蠕变  本构模型  遗传算法  有限元  填石路堤  反分析
文章编号:1000-7598-(2006)08-1299-06
收稿时间:2004-11-06
修稿时间:2004-11-062005-03-05

Study on constitutive model and its parameter''''s back analysis of creep deformation for the high rockfill embankment and their application
CAO Wen-gui,LI Peng,CHENG Ye. Study on constitutive model and its parameter''''s back analysis of creep deformation for the high rockfill embankment and their application[J]. Rock and Soil Mechanics, 2006, 27(8): 1299-1304
Authors:CAO Wen-gui  LI Peng  CHENG Ye
Affiliation:1.Geotechnical Engineering Institute, Hunan University, Changsha 410082, China;2.Hunan Bureau of Expressway Administration, Changsha 410076,China
Abstract:Based on practical measuring data in engineering, the hyperbola-shaped constitutive model which has three parameters and reflects the law of creep deformation after construction for high rockfill embankment is firstly proposed by combing the mechanism of settlement with the features of engineering; and the back-analysis way that the model’s parameters are determined has been brought forward with introduction of genetic algorithm and finite element method. Afterwards,the computational means of the settlement after construction for high rockfill embankment is deeply discussed using finite element method for creep; and the relevant analytic software is developed. Finally, the application for the constitutive model proposed in this paper and the computational method of the settlement for high rockfill embankment is deeply probed by combining with the practices of engineering. It is indicated by analysis of the example of practical engineering that both the constitutive model for creep deformation and the computational means of settlement after construction are simple and reach the request of engineering practice, and a new computational method for the after-construction settlement of high rockfill embankment which is elementarily established
Keywords:creep   constitutive model   genetic algorithm   finite element method   rockfill embankment   back analysis