首页 | 本学科首页   官方微博 | 高级检索  
     检索      

高铁单点交错轨道平面和高程控制网测设新方法研究
引用本文:刘强,游为,刘成龙,杨雪峰,王欢.高铁单点交错轨道平面和高程控制网测设新方法研究[J].测绘与空间地理信息,2020(3):64-67,72.
作者姓名:刘强  游为  刘成龙  杨雪峰  王欢
作者单位:西南交通大学地球科学与环境工程学院;西南交通大学高速铁路运营安全空间信息技术国家地方联合工程实验室
基金项目:长江学者和创新团队发展计划(IRT13092)资助。
摘    要:为提高高速铁路轨道控制网(CPⅢ)建网及复测的效率,提出单点交错形式三维CPⅢ控制网测设新方法。该方法采用单点交错的布点方式,较点对形式的CPⅢ控制网CPⅢ控制点数量减半;该方法采用全站仪一次测量同时构建CPⅢ平面网和CPⅢ三角高程网,测量效率显著提高。为验证该方法的精度及可行性,对某段高速铁路CPⅢ控制网实测数据进行计算实验。结果表明,该方法求得的坐标与传统点对形式的CPⅢ控制点坐标的较差落入-1 mm,1 mm]区间的概率为98.9%,求得的高程与矩形法水准高程的较差落入-3 mm,3 mm]区间的概率为97%,说明按照本文方法构建的CPⅢ平面网及CPⅢ三角高程网,均满足高铁CPⅢ控制网的精度要求。

关 键 词:点对形式  单点交错形式  CPⅢ平面网  CPⅢ高程网  精度

The New Surveying Method of Single Point Interleaved Horizontal and Vertical Control Network for High-speed Railway Tracks
LIU Qiang,YOU Wei,LIU Chenglong,YANG Xuefeng,WANG Huan.The New Surveying Method of Single Point Interleaved Horizontal and Vertical Control Network for High-speed Railway Tracks[J].Geomatics & Spatial Information Technology,2020(3):64-67,72.
Authors:LIU Qiang  YOU Wei  LIU Chenglong  YANG Xuefeng  WANG Huan
Institution:(Faculty of Geosciences and Environmental Engineering,Southwest Jiaotong University,Chengdu 611756,China;State-Province Joint Engineering Laboratory in Spatial Information Technology forHigh-Speed Railway,Chengdu 611756 China)
Abstract:In order to improve the efficiency of the construction and re-measurement of the high-speed railway track control network( CPⅢ),a new surveying method of single point interleaved three-dimensional CPⅢ control network is proposed. As compared with the normal CPⅢ control network,the number of control points in this study is half reduced by placing them in an interleaved pattern.The CPⅢ horizontal network and CPⅢ trigonometric vertical network are constructed by one-time total station survey,and the surveying efficiency is greatly improved.In order to verify the accuracy and feasibility of this method,a computational experiment is carried out by using the measured data of CPⅢ control network of a high-speed railway. By comparing the difference between the coordinates obtained by this method and the traditional point pair form CPⅢ horizontal network,the probability of the differences falling into the-1 mm,1 mm]interval takes up 98.9%. The probability of the difference between the elevation obtained by this method and the rectangular method falling into the -3 mm,3 mm]interval takes up 97%.It demonstrates that the CPⅢ horizontal network and the CPⅢ triangular vertical network constructed in this method can meet the precision requirements of the high-speed railway CPⅢ control network.
Keywords:point pair form  single point interleaved form  CPⅢ horizontal network  CPⅢ vertical network  accuracy
本文献已被 CNKI 维普 等数据库收录!
设为首页 | 免责声明 | 关于勤云 | 加入收藏

Copyright©北京勤云科技发展有限公司  京ICP备09084417号