首页 | 本学科首页   官方微博 | 高级检索  
     检索      

金龙沟泥石流
引用本文:何其修.金龙沟泥石流[J].山地学报,1991(1).
作者姓名:何其修
作者单位:水电部成都勘测设计院
摘    要:紧靠二滩水电站导流硐进口的金龙沟支流,泥石流活动频繁,来量丰富。为了确保电站施工安全,本文在调查研究的基础上,对泥石流的流型、峰值、过程总量进行了估算;同时根据泥石流来量的大小,提出了控制泥石流的几种工程硬措施。

关 键 词:金龙沟  泥石流  调查访问  峰值估算  控制

DEBRIS FLOWS OF THE JINLONG GULLY
He Qixiu.DEBRIS FLOWS OF THE JINLONG GULLY[J].Journal of Mountain Research,1991(1).
Authors:He Qixiu
Abstract:The Jinlong Gully is near the diversion intake of Ertan Hydroeletric Power Station. Here, the debris flow activities are frequent. Debris flowit once occurs will bring a inestimable loss to the construction of the hydroeletric power station. In order to ensure the safety in construction of the arch dam, the actual investigation on this gully was carried out. Based on the analysis of physical geography,hydrologic and climatic characteristics of the Jinlong Gully,and formation conditions and developing tendency of debris flow,a rational design for the engineering measures to prevent and control debris flows was given.
Keywords:the Jinlong Cully  debris flow  actual investigation  contral
本文献已被 CNKI 等数据库收录!