昆明新南亚风情园静压桩浮桩原因及复压法处理技术
引用本文:李志江.昆明新南亚风情园静压桩浮桩原因及复压法处理技术[J].探矿工程,2009,36(4):55-58.
作者姓名:李志江
作者单位:云南国土建设工程总公司昆明分公司,云南昆明650102
摘    要:昆明新南亚风情园基础设计为静压预制管桩,试桩承载力等参数满足设计要求,但工程桩施工完毕,进行检测时发现浮桩。通过分析浮桩的原因,采取复压处理方案,各项参数符合设计要求。总结了静压桩施工和浮桩处理的经验和体会。

关 键 词:静压预制管桩  浮桩  挤土效应(应力)  超孔隙水压力  承载力  复压
收稿时间:2008/7/16 0:00:00

Cause of Static Pressure Pile Floating and Repressing Treatment
LI Zhi-jiang.Cause of Static Pressure Pile Floating and Repressing Treatment[J].Exploration Engineering(Drilling & Tunneling),2009,36(4):55-58.
Authors:LI Zhi-jiang
Institution:LI Zhi-jiang ( Kunming Branch, Yunnan Land Construction Engineering Co. , Ltd. , Kunming Yunnan 650102, China)
Abstract:The foundation of Nanyafengqing Garden was designed of static pressure pre-cast tube pipe; pile floating was detected after construction. Through the cause analysis, repressing treatment scheme was applied with parameters satisfying the design requirement.
Keywords:static pressure pre-cast tube pipe  pipe floating  compaction effect  excess pore water pressure  bearing capacity  repressing