东升电站堆石混凝土重力坝固结灌浆工程
引用本文:娄广辉,姜鹏飞,刘卫卫.东升电站堆石混凝土重力坝固结灌浆工程[J].吉林地质,2011,30(4):95-98.
作者姓名:娄广辉  姜鹏飞  刘卫卫
作者单位:吉林大学建设工程学院,吉林长春,130000
摘    要:东升水电站挡水建筑物采用堆石混凝土重力坝,基础固结灌浆过程中发现钻孔施工难度较大,采用了先对抛石段灌浆,后钻孔,再整体固结灌浆的方法,解决了这一问题,提高了整体的施工效率,经检验,固结灌浆效果明显,达到了设计要求。

关 键 词:东升电站  堆石混凝土坝  固结灌浆

Consolidation grouting engineering of concrete rockfill dam of Dongsheng power station
LOU Guang-hui,JIANG Peng-fei,LIU Wei-wei.Consolidation grouting engineering of concrete rockfill dam of Dongsheng power station[J].Jilin Geology,2011,30(4):95-98.
Authors:LOU Guang-hui  JIANG Peng-fei  LIU Wei-wei
Institution:College of Construction Engineering,Jilin University,Changchun130000,Jilin,China
Abstract:Dongsheng station uses rockfill concrete gravity retaining structures,it is difficult in foundation consolidation grouting in drilling construction.According to specific circumstances,firstly,we threw stones,grouted,and drilled,then,the overall consolidation grouted solutions to solve this problem.It improves the overall efficiency of construction,and inspection,consolidation grouting effect is obvious,and meets the design requirements.
Keywords:Dongsheng power station  concrete rockfill dam  consolidation grouting