梯级水电站多目标发电优化调度
引用本文:覃晖,周建中,肖舸,赵云发,卢有麟,张勇传.梯级水电站多目标发电优化调度[J].水科学进展,2010,21(3):377-384.
作者姓名:覃晖  周建中  肖舸  赵云发  卢有麟  张勇传
作者单位:1.华中科技大学水电与数字化工程学院, 湖北, 武汉, 430074;
基金项目:"十一五"国家科技支撑计划重点资助项目,公益性行业科研专项经费资助项目,国家自然科学基金重点资助项目 
摘    要:以发电量和保证出力为目标建立梯级水电站的多目标发电优化调度模型,对三峡梯级中长期发电优化调度进行研究。针对传统方法求解多目标优化问题的局限,提出一种强度Pareto差分进化算法(Strength Pareto Differential Evolution,SPDE)用于求解梯级水电站的多目标发电优化调度问题。SPDE以差分进化算法(Differential Evolution,DE)为基础,采用SPEA2的适应度评价方法,并根据多目标优化的特点对DE的进化算子进行修正。同时,提出一种自适应柯西变异策略(Adaptive Cauchy Mutation,ACM)用于克服算法的早熟收敛问题。三峡梯级水电站实例研究结果表明,SPDE可同时考虑两个目标并有效处理复杂约束条件,一次运行即可得到一组在各目标分布均匀、分布范围广的非劣调度方案供决策者评价优选。

关 键 词:梯级水电站    发电调度    多目标优化    差分进化算法    非劣调度方案集
收稿时间:2009-06-11

Multi-objective optimal dispatch of cascade hydropower stations using strength Pareto differential evolution
QIN Hui,ZHOU Jian-zhong,XIAO Ge,ZHAO Yun-fa,LU You-lin,ZHANG Yong-chuan.Multi-objective optimal dispatch of cascade hydropower stations using strength Pareto differential evolution[J].Advances in Water Science,2010,21(3):377-384.
Authors:QIN Hui  ZHOU Jian-zhong  XIAO Ge  ZHAO Yun-fa  LU You-lin  ZHANG Yong-chuan
Institution:1.Huazhong University of Science and Technology, Wuhan 430074, China;2.Three Gorges Cascade Dispatching & Communication Center, Yichang 443133, China
Abstract:A multirobjective optimization model for operating cascade hydropower stations is established.The model can maximize both firm power and annual energy production simultaneously.The model is solved using the strength Pareto differential evolution(SPDE) approach.The latter is a novel extension of the Differential Evolution (DE) algorithm to multirobjective optimization problems.SPDE adopts the fitness assign method used in the strength Pareto evolution approach 2(SPFA2),andmodifies theDE operators according to the characteristic of multir-objective optimination.An adaptive Cauchy mutation (ACM) is also used to prevent premature convergence.The model is tested using a case of Three Gorges cascade hydropower stations.The result shows that SPDE is able to simultaneously consider the two optimization objectives and effectively dealwith complex constraints.A setof alternative non-dominated schemes with uniform coverage can be provided for decision making, which presents a viable alternative formultirobjective optimal dispatch of cascade hydropower stations.Our result could be used as a reference formaking the midbmg teffn generation scheduling schemes for Three Gorges cascade hydropower stations.
Keywords:cascade hydropower stations  generation scheduling  multi-objective optinization  differential evolution  non-dom mated schemes  