九道岭煤矿贯通测量方案设计与新方法研究
引用本文:张凤琴,车延国.九道岭煤矿贯通测量方案设计与新方法研究[J].测绘工程,2008,17(3):62-65.
作者姓名:张凤琴  车延国
作者单位:盘锦市国土资源征地勘测处,辽宁,盘锦,124010;辽宁工程技术大学,辽宁,阜新,123000
摘    要:设计了两套九道岭煤矿副井与西风井之间-700m水平大巷贯通测量方案,并从精度和工程预算等方面分析了其优缺点,选出最优方案。讨论了井下导线加测陀螺边的优点,提出测陀螺边的最佳位置为2i/(2m+1)L (L为导线全长,适用等边直伸型导线),最佳条数为1~2条。

关 键 词:贯通测量  精度预计  陀螺定向  最佳位置  最佳条数

A new method for hole-link up surveying plan design
ZHANG Feng-qin,CHE Yan-guo.A new method for hole-link up surveying plan design[J].Engineering of Surveying and Mapping,2008,17(3):62-65.
Authors:ZHANG Feng-qin  CHE Yan-guo
Institution:ZHANG Feng-qin1,CHE Yan-guo2
Abstract:Two surveying plans were designed about the-700m Hole-Links up between west wind shaft and auxiliary shaft of Jiudaoling coal mine,and the better plan is selected by final accuracy and total cost.The advantage of combining baseline and survey gyro compassing side method is disccused.The best position for survey gyro compassing side should be (2i/2m 1)L(L is the span of traverse,it is suitable for the equilateral straight traverse).the best number of baseline is 1 to 2.
Keywords:Hole-Links up surveying  precision estimate  gyroscope orientation  the best position  The best number of baseline