三峡水库动态汛限水位洪水调度风险指标及综合评价模型研究
引用本文:王才君,郭生练,刘攀,周芬,熊立华.三峡水库动态汛限水位洪水调度风险指标及综合评价模型研究[J].水科学进展,2004,15(3):376-381.
作者姓名:王才君  郭生练  刘攀  周芬  熊立华
作者单位:武汉大学水资源与水电工程科学国家重点实验室, 湖北武汉, 430072
基金项目:水利部重大科研资助项目,湖北省自然科学基金资助项目(2002AB009)~~
摘    要:汛限水位是综合利用水库运行和调度的重要参数之一,也是协调防洪和兴利矛盾的焦点所在。现行的汛限水位过多地考虑了小概率洪水事件,不能充分挖掘水库汛期的兴利效益,因此,采用动态汛限水位进行调度,对综合利用水库的运行具有重要的理论意义和实用价值。根据三峡水库围堰发电期的调度规程,建立预报预泄调度模型,采用宜昌站1882-2001年汛期实测日流量资料,实现了考虑预报信息的动态汛限水位洪水调度模拟;提出了多目标风险指标体系;计算了9种动态汛限水位方案下的风险指标值,通过综合评价模型对各方案进行比较和优选,得到了相对合理的动态汛限水位方案。

关 键 词:三峡水库    动态汛限水位    洪水调度    风险分析    综合评价模型
文章编号:1001-6791(2004)03-0376-06
收稿时间:2003-01-17
修稿时间:2003年1月17日

Risk criteria and comprehensive evaluation model for the operation of Three Gorges reservoir under dynamic flood limit water level
WANG Cai-jun,GUO Sheng-lian,LIU Pan,ZHOU Fen,XIONG Li-hua Wuhan University,Wuhan ,China.Risk criteria and comprehensive evaluation model for the operation of Three Gorges reservoir under dynamic flood limit water level[J].Advances in Water Science,2004,15(3):376-381.
Authors:WANG Cai-jun  GUO Sheng-lian  LIU Pan  ZHOU Fen  XIONG Li-hua Wuhan University  Wuhan  China
Affiliation:State Key Laboratory of Water Resources and Hydropower Engineering Science, Wuhan University, Wuhan 430072, China
Abstract:As a key parameter of multi-purpose reservoir operation, flood limit water level plays a critical role in achieving the balance between flood control and economic benefit such as hydro-power generation and navigation improvement etc. The currently adopted flood limit water level pays too much attention to the floods of low probability, thus reducing the economic benefit of the reservoir during the flood period. It is theoretically and applicably essential to adopt a dynamic flood limit water level in the operation. According to the general operation rules of Three Gorges Reservoir (TGR), a real-time model under dynamic flood limit water level is developed and used to simulate the TGR operation by using the daily river flow series of the Yichang gauging station about 40 km downstream to the dam site of the TGR during the period of 1882-2001. The multi-objective criteria and a comprehensive evaluation model are proposed and developed to measure and assess the TGR operation risks. The optimum scheme is obtained by comparing nine alternatives of dynamic flood limit water level schemes.
Keywords:Three Gorges reservoir  dynamic flood limit water level  flood operation  risk analysis  comprehensive evaluation model
本文献已被 CNKI 维普 万方数据 等数据库收录!
点击此处可从《水科学进展》浏览原始摘要信息
点击此处可从《水科学进展》下载全文